BID TABULATION
53-18AUG05 Sheriff's Department North Substation Site Work
Christensen Construction Co.
Description Qty Unit Unit Price Extended Price
Mobilization 1 LS $3,500.00 $3,500.00
Earthwork 460 CY $8.00 $3,680.00
Silt Fence 400 LF $4.50 $1,800.00
Erosion Control Mat (Ditch Liner) 115 SY $6.00 $690.00
2 1/2" Compact Aggregate Base (4" thickness) 890 SY $3.76 $3,346.40
1 1/2" Compacted Aggregate Base (4" thickness) 849 SY $3.76 $3,192.24
Two (2) applications of Chip & Seal Surfacing 808 SY $6.58 $5,316.64
Unsuitable Subgade Repair 10 CY $50.00 $500.00
Base Bid Total   $22,025.28