BID
TABULATION |
|
|
|
|
|
|
|
|
|
|
45-14JUL05 Lake of the Woods Pavement & Drainage
Improvements Phase I |
|
|
|
|
|
|
|
APAC-MISSOURI
INC |
STEVE AND ASSOCIATES |
LEHMAN CONSTRUCTION LLC |
EMERY SAPP & SONS |
|
QTY |
Unit |
Unit Price |
Extended Price |
Unit Price |
Extended Price |
Unit Price |
Extended Price |
Unit Price |
Extended Price |
Mobilization
and Bonds |
1 |
LS |
$13,000.00 |
$13,000.00 |
$18,358.27 |
$18,358.27 |
$10,500.00 |
$10,500.00 |
$22,000.00 |
$22,000.00 |
Construction
Staking |
1 |
LS |
$2,850.00 |
$2,850.00 |
$2,840.42 |
$2,840.42 |
$3,500.00 |
$3,500.00 |
$3,500.00 |
$3,500.00 |
Traffic
Control |
1 |
LS |
$1,700.00 |
$1,700.00 |
$5,375.00 |
$5,375.00 |
$8,000.00 |
$8,000.00 |
$6,500.00 |
$6,500.00 |
Removals
of Improvements |
1 |
LS |
$37,600.00 |
$37,600.00 |
$26,973.63 |
$26,973.63 |
$20,000.00 |
$20,000.00 |
$33,500.00 |
$33,500.00 |
Excavation
and Embarkment |
1 |
LS |
$16,150.00 |
$16,150.00 |
$16,240.02 |
$16,240.02 |
$5,000.00 |
$5,000.00 |
$12,500.00 |
$12,500.00 |
6"
Concrete Pavement (Main Line) |
4487 |
SY |
$38.25 |
$171,627.75 |
$28.63 |
$128,462.81 |
$39.00 |
$174,993.00 |
$22.00 |
$98,714.00 |
6"
Concrete Driveway Pavement |
502 |
SY |
$57.30 |
$28,764.60 |
$46.26 |
$23,222.52 |
$46.00 |
$23,092.00 |
$58.00 |
$29,116.00 |
4"
Type I Aggregate Base |
4989 |
SY |
$4.90 |
$24,446.10 |
$4.32 |
$21,552.48 |
$6.00 |
$29,934.00 |
$5.00 |
$24,945.00 |
Type M
Inlet #1 4' x3' x8.1' Modified Throat |
1 |
EA |
$3,325.00 |
$3,325.00 |
$3,428.36 |
$3,428.36 |
$3,250.00 |
$3,250.00 |
$3,000.00 |
$3,000.00 |
Type M
Inlet # 2 4' x3' x 5.3' |
1 |
EA |
$2,800.00 |
$2,800.00 |
$2,912.36 |
$2,912.36 |
$2,800.00 |
$2,800.00 |
$3,000.00 |
$3,000.00 |
18"
Corrugated Metal Pipe (CMP) 16 GA |
57.5 |
LF |
$65.15 |
$3,746.13 |
$75.90 |
$4,364.25 |
$45.00 |
$2,587.50 |
$70.00 |
$4,025.00 |
Type 2
Rip-Rap Blanket |
2 |
CY |
$130.00 |
$260.00 |
$623.06 |
$1,246.12 |
$60.25 |
$120.50 |
$110.00 |
$220.00 |
Remove
and Replace unsuitable Subgrade |
150 |
CY |
$30.50 |
$4,575.00 |
$45.75 |
$6,862.50 |
$38.00 |
$5,700.00 |
$35.00 |
$5,250.00 |
Fertilize,
Seed, Mulch & Site Restoration |
1 |
LS |
$6,400.00 |
$6,400.00 |
$3,877.09 |
$3,877.09 |
$4,000.00 |
$4,000.00 |
$6,000.00 |
$6,000.00 |
Erosion
Control Barrier |
1 |
LS |
$10,175.00 |
$10,175.00 |
$2,150.00 |
$2,150.00 |
$4,000.00 |
$4,000.00 |
$1,000.00 |
$1,000.00 |
BASE BID TOTAL |
|
$94,326.10 |
$327,419.58 |
$82,979.07 |
$267,865.83 |
$61,284.25 |
$297,477.00 |
$91,300.00 |
$253,270.00 |
|
|
|
ALTERNATE
#1 |
|
|
|
|
|
Mobilization
and Bonds |
1 |
LS |
$4,825.00 |
$4,825.00 |
$2,418.75 |
$2,418.75 |
$2,000.00 |
$2,000.00 |
$4,200.00 |
$4,200.00 |
Traffic
Control |
1 |
LS |
$1,685.00 |
$1,685.00 |
$2,687.50 |
$2,687.50 |
$2,000.00 |
$2,000.00 |
$1,200.00 |
$1,200.00 |
Full
Depth Concrete Pavement Repair |
490 |
SY |
$120.00 |
$58,800.00 |
$86.42 |
$42,345.80 |
$48.00 |
$23,520.00 |
$55.00 |
$26,950.00 |
6"
Concrete Driveway Pavement |
115 |
SY |
$58.25 |
$6,698.75 |
$99.98 |
$11,497.70 |
$60.00 |
$6,900.00 |
$58.00 |
$6,670.00 |
Concrete
Pavement Removal |
605 |
SY |
$39.50 |
$23,897.50 |
$43.83 |
$26,517.15 |
$13.00 |
$7,865.00 |
$50.00 |
$30,250.00 |
Fertilize,
Seed, Mulch and site Restoration |
1 |
LS |
$2,125.00 |
$2,125.00 |
$1,612.50 |
$1,612.50 |
$1,400.00 |
$1,400.00 |
$2,500.00 |
$2,500.00 |
Remove
and Replace Unsuiteable Subgrade |
60 |
CY |
$31.50 |
$1,890.00 |
$71.94 |
$4,316.40 |
$38.00 |
$2,280.00 |
$60.00 |
$3,600.00 |
|
|
|
ALTERNATE
BID TOTAL |
|
|
|
$99,921.25 |
|
$91,395.80 |
|
$45,965.00 |
|
$75,370.00 |
|
|
|
|
|
|
Bidder's
Qualifications |
|
|
Yes |
|
Yes |
|
Yes |
|
Yes |
|
Anti-Collusion
statement |
|
|
Yes |
|
Yes |
|
Yes |
|
Yes |
|
Signature
& Identity of Bidder |
|
|
Yes |
|
Yes |
|
Yes |
|
Yes |
|
Bidder's
Acknowledgment |
|
|
Yes |
|
Yes |
|
Yes |
|
Yes |
|
Bid
Bond |
|
|
Yes |
|
Yes |
|
Yes |
|
Yes |
|
|
|
|
|
|
|
|
|
|
|
|