- Concrete/Cement Term and Supply |
|
|
|
|
|
|
4.7. |
PRICING
- READY MIX CONCRETE |
Central Concrete |
Columbia
Ready Mix |
|
|
|
Description |
Estimated
Quantity |
Unit of
Measure |
Unit
Price |
Extended
Price |
Unit
Price |
Extended
Price |
|
|
|
|
4.7.1. |
Five
(5) Bag Mix, 3500 PSI 28 Days |
100
cubic yards |
cubic
yard |
46.00 |
$ 4,600.00 |
$ 56.65 |
$ 5,665.00 |
|
|
4.7.2. |
Six
(6) Bag Mix, 4500 PSI 28 Days |
600
cubic yards |
cubic
yard |
48.50 |
$ 29,100.00 |
$ 59.65 |
$ 35,790.00 |
|
|
4.7.3 |
3500PSI
in 3 hours (8 Bag Mix, Minimum - High Early) without
Transportation |
100
cubic yards |
cubic
yard |
54.75 |
$ 5,475.00 |
$ 61.25 |
$ 6,125.00 |
|
|
4.7.4. |
Maximum
Delivery Time Included in Cost |
|
hours |
2
hrs |
|
1 hr |
|
|
|
4.7.5 |
Transportation |
|
|
|
|
|
|
|
|
4.7.5.1 |
Full
Load Rate>3CY/full load |
|
|
19.00 |
|
$ 15.75 |
|
|
|
4.7.5.2 |
Short
Load Rate |
|
|
|
|
|
|
|
|
4.7.5.2.1 |
Less
than one yard |
|
|
1yrd
min |
|
$ 40.00 |
|
|
|
4.7.5.2.2 |
1-
1/4 to 2 yards |
|
|
$ 25.00 |
|
$ 40.00 |
|
|
|
4.7.5.2.3 |
2-1/4
to 3 yards |
|
|
$ 25.00 |
|
$ 40.00 |
|
|
|
4.7.5.2.4 |
Holding
Charges |
|
|
25.00/hr |
|
$ 55.00 |
|
|
|
4.7.5.3 |
Stop
Rate (charge to stop at other job sites to complete the delivery over _______
mile apart (Bidder must complete the mileage blank) |
|
|
2
mile/$20.00 |
|
5
mile/$27.50 |
|
|
|
4.7.6 |
Extra
Charges |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.7.6.1 |
Winter
Service (Hot Water) Add |
|
cubic
yard |
$ 3.00 |
|
$ 3.00 |
|
|
|
4.7.6.2 |
Calcium
Chloride, 1/2% Add |
|
cubic
yard |
$ 0.75 |
|
$ 0.75 |
|
|
|
4.7.6.3 |
Calcium
Chloride, 1% Add |
|
cubic
yard |
$ 1.50 |
|
$ 1.50 |
|
|
|
4.7.6.4 |
Calcium
Chloride, 2% Add |
|
cubic
yard |
$ 3.00 |
|
$ 3.00 |
|
|
|
4.7.6.5 |
Summertime
Retarder Add |
|
cubic
yard |
$ 4.00 |
|
$ 2.50 |
|
|
|
4.7.6.6 |
Indicate
any additional charges not included above. |
|
|
No Response |
No Response |
|
|
4.8. |
PRICING
- MISCELLANEOUS MATERIALS |
|
|
|
|
|
|
|
Description |
Estimated
Quantity |
Unit
of Measure |
Unit
Price |
Extended
Price |
Unit
Price |
Extended
Price |
|
|
4.8.1. |
Reinforcing
Steel Rod. 1/2 X 20’ |
400 |
each |
5.00 |
$ 2,000.00 |
$ 5.95 |
$ 2,380.00 |
|
|
|
|
4.8.2. |
Wire
Mesh, 10 ga. 6” x 6” mesh |
10 |
each |
n/a |
n/a |
$ 75.00 |
$ 750.00 |
|
|
|
|
4.8.3. |
Expansion
Board, 1/2” x 4” x 5’ |
100 |
each |
1.75 |
$ 175.00 |
$ 2.15 |
$ 215.00 |
|
|
|
|
4.8.4. |
Reinforcing
Steel Rod, 5/8” x 20’ |
200 |
each |
n/a |
n/a |
$ 7.50 |
$ 1,500.00 |
|
|
|
|
4.8.5. |
Reinforcing
Steel Rod, 3/4” x 20’ |
200 |
each |
n/a |
n/a |
n/a |
n/a |
|
|
|
|
4.8.6. |
5”
Loop Ties (5,000 per Roll) |
5 |
per
roll |
n/a |
n/a |
$
55.00 |
$ 275.00 |
|
|
|
|
4.8.7. |
7”
Loop Ties (5,000 per Roll) |
5 |
per
roll |
n/a |
n/a |
$ 75.00 |
$ 375.00 |
|
|
|
|
4.8.8. |
9”
Loop Ties (5,000 per Roll) |
5 |
per
roll |
n/a |
n/a |
$ 75.00 |
$ 375.00 |
|
|
|
|
4.10. |
Co-op |
no |
no |
|
|
4.11. |
Delivery
Days After Receipt of Order:
_____________________________________________ |
12-24 hr notice |
1 day |
|
|
4.12. |
Maximum Percentage
Increase for 2nd Year |
n/a |
|
n/a |
|
|
|
|
|
Maximum Percentage
Increase for 3rd Year |
n/a |
n/a |
|
|
|
No Bids |
|
Opened By: Melinda Bobbitt |
|
|
|
|
Boone County Ready-Mix, LLC |
Recorded By: Kerry Patton |
|
|
Date: April
26, 2005, 10:33 a.m. |
|
|
|
|
|
|
|
|
|
|
|
|
|